Client: Lagan/ Ferrovial
Value: £1.4m
Summary of Albion Works:
- 330,000m³ rock blasting (1m t)
- 10,000 m² pre-split
- 2,750m stitch drilling
- Blasting at five locations
- Atlas-Copco L6 drill rigs
- Blasting 3 times a week
Technical Difficulties:
- Properties as close as 25m
- Adjacent to Belfast-Dublin main line and the existing bypass